DuPont schedule explained
The DuPont schedule is a 12-hour rotation for plants and other sites that run day and night. Each crew works a mix of day and night shifts over a 28-day cycle and then takes a full week off. It is called a DuPont rota in the UK and a DuPont roster in Australia and New Zealand.
The DuPont schedule calendar shows your own dates from one night you worked. This guide explains why the pattern is shaped the way it is.
The 28-day cycle
One crew's four weeks run like this:
- 4 night shifts.
- 3 days off. The first is a rest day, the day you finish in the morning and sleep.
- 3 day shifts.
- 1 day off.
- 3 night shifts.
- 3 days off, starting with a rest day.
- 4 day shifts.
- 7 days off in a row.
That is 14 shifts of 12 hours in 28 days, 168 hours, or 42 hours a week on average. The cycle then starts again with 4 nights.
How four crews cover the plant
A DuPont site splits its people into four crews, A to D. Each crew runs the same 28-day cycle, starting a week after the crew before it. Laid side by side, the four crews fit together exactly: on every day of the cycle one crew is on days, one is on nights, and two are off. Every shift is covered by exactly one crew.
That fit is the reason the pattern looks irregular. The runs of 4, 3, 3 and 4 are what make four staggered copies of the cycle cover every day and every night with one crew each.
The 7-day break
Every crew gets a full week off once every four weeks. Seven days in a row always include a Saturday and a Sunday, so every crew is off on both each cycle. The 7-day break comes straight after 4 day shifts, so the last day shift ends in the evening and the week off starts the next morning.
The short breaks
The shortest break is the single day off between the 3 day shifts and the 3 night shifts. It moves you from days to nights in one step. The two 3-day breaks after nights each start with a rest day, so you have two full days after you have slept off the last night.
DuPont compared with other 12-hour patterns
All three of these put a crew on 12-hour shifts for half the days of the year, around 2,190 hours on the clock:
| Cycle | Longest break | Shifts per crew per cycle | |
|---|---|---|---|
| DuPont | 28 days | 7 days | 14 |
| Panama | 28 days | 3 days | 14 |
| 4 on 4 off | 8 days | 4 days | 4 |
The difference is how the time off is grouped. DuPont saves it up for a week off; Panama spreads it into 2- and 3-day breaks; 4 on 4 off gives a 4-day break every 8 days.
Seeing your own DuPont schedule
Open the DuPont calendar, choose the first of 4 nights you worked, and every date follows. Under More you can pick your crew letter to label your shifts, add the whole schedule to your phone's calendar, or print a year.